Ackerman Wastewater Expansion

项目描述

The Ackerman MSBU was approved in November 2019. This project includes construction of a wastewater collection system to service approximately 1,300 properties with sewer service, new water service lines and a vacuum station that will provide sewer collection for the wastewater system. 

项目的更新
  • Zones 1 and 2 connections have begun. You will receive a door hanger approximately a week prior to connection of your home.
    • 承包商:Rohaley & Sons Plumbing Contractors Inc.
    • Total Connections as of March: 315
  • The vacuum station is operational. 
  • Installation Agreements for zones 1 and 2 have been mailed out. Please be sure to sign and return them to the 公用事业公司 Department as soon as possible.
  • 建设 of the water line replacement and sewer main installation in zones 1 and 2 is complete. The vacuum station is currently operational.
  • The BCC approved the contract for the Vacuum Station and zones 1 and 2. Contractor: Guymann 建设 of Florida, Inc. 

Capital Projects Office
电话:941.764.4305
电子邮件: S2S@CharlotteCountyFL.政府

项目位置

Throughout the Ackerman Avenue neighborhood. 

建设 materials are being stored at the corner of Ohara Drive and Midway Boulevard.

The vacuum station located at, 18330 Ackerman Avenue is currently operational.

项目的影响

Residents in the Ackerman project area may experience low water pressure for the next few months. Crews are currently transferring over to the water new lines and flushing to keep chlorine residuals up in the area. Work also includes connecting customers to the newly installed lines. 

Crews are encountering large amounts of rock during excavation, which has resulted in an unplanned rock crushing operation at the construction yard. 

最新的更新

Installation Agreements for zone 1 and 2 have been mailed out. Please be sure to sign and return them to the 公用事业公司 Department as soon as possible. These forms give CCU permission to come on to your lot with a plumber to connect your home to the central sewer line currently being installed. This work is included in your MSBU assessment, and there are no additional costs. For questions, 联系: Syndi Merriman at 941-764-4305 or S2S@CharlotteCountyFL.政府

Vacuum station is operational. Zone 1 water complete and vacuum sewer complete. Zone 2 water complete and vacuum sewer started. Zones 1 and 2 connections have begun.

Zones 3, 4 and LPS design complete. 建设 is expected to start by the end of 2024.

预算

阶段 成本
总预算 $26,948,870.00
资金来源:

居民的评估, Florida Department of Environmental Protection State Revolving Funds, 美国环保署资助, 恢复, Utility Repair and Replacement Funds.

时间表

阶段 预计开始日期 预计完成 实际完成
规划及审批 11/19/2019 12/01/2020 12/01/2020
设计开发 01/21/2021 02/01/2022 02/01/2022
建设 04/05/2021 11/30/2026

支持材料

项目阶段
建设

最后一次更新
04/16/2024

项目经理
迈克Martindell

公共关系
卡洛琳Wannall
Email 公共关系

支持部门
公用事业公司

Design Engineer/Architect
Giffels-Webster Engineers

建设 Contractor
Guymann 建设 of Florida, Inc.

Delivering Exceptional Service

问题? 问题?

澳门正规网赌网址大全